  • Owner: Agricultural Development Association (PARC)
  • Location: Gaza strip
  • Duration: 2020-2020
  • Type of Services:
      Assess the proposed construction locations

    The consultant will develop selection criteria in a participatory manner to be used by the consultant in assessing the proposed locations for the construction of the desalination plant. The location areas will be submitted by MoA and it will be around 10 Locations, taking into account:

    • The well water salinity level, in terms of total dissolved solids (TDS), is between 1000 ppm to 2000 ppm
    • The availability of the electrical power in the proposed location
    • The location is not planned to be irrigated by either imported water (MEKOROT) or treated wastewater within the next 10 years.
    • The well capacity is suitable for installing the proposed desalination plant.
    • The farmers in the target area plant drought-resilient crops.
    • Sun availability, flat landscape, disposal of the environmental obstacles
    Design the desalination plant along with full tender document:

    After selecting the construction location, the consultant will design the desalination plant and prepare all the design documents, including but not limited to:

    • Water and soil test reports
    • Inspection report including the proposed methodology
    • Solar system that fits to feed the station which will be fit both systems solar and desalination systems
    • Estimated cost and cash flow
    • Bill of quantities
    • Time schedule
    • Method statement
    • Detailed tender drawings, including the civil, mechanical and electrical works
    • Technical specifications (general and special)

    Based on designated location, the consultant will be responsible for fully developing the tender documents that develop the specifications and descriptions for each item that will be requested from the contractors/suppliers in addition to being part of the technical committee which will evaluating the tenderer.

    Follow up the construction work:

    The consultant will be responsible for following up all the construction work of the desalination plant, including, but not limited to, the following:

    • Direct technical supervision all the process of implementing the desalination unit and the solar system
    • Reporting to the project team about the progress of the implementation
    • Documenting the implementation process by reports, photos and video films
  • Note: